Before starting upgrade:
- Patch portal to 7.3.5 on dev, qa and live (11/9 - 11/10)
- Test with the patch before starting upgrade (11/11 - 11/12)
- Change oracle driver class name in vcm config and tomcat conf to oracle.jdbc.driver.OracleDriver
Timeline for upgrade:
- Dev: 5 days
- QA: 5 days
- QA: migration to 64bit - 5 days (on VM and use QA hardware for Prod 64bit?)
- Load testing: 5 days
- Prod: 10 days
- Prod migration to 64bit - 5 days
Follow the Upgrade guide
Order of servers upgrade QA/Prod:
- VCM
- Autonomy
- QA1 & QA2, should be upgrade together, so requires downtime, writedown each step before continuing (Estimate downtime: 8 hrs)
Rough roadmap for VCM upgrade:
- Uninstall CCE
- Backup Autonomy
- Uninstall Autonomy
- Stop endpoints
- Stop services
- install 7.6
- run vgnupgrade
- Rename old Contnent/7_3_1 directory
- Upgrade Autonomy
- Post upgrade stuff from ch7
- Custom CMA and other apps deployments
- DPM deployments, config changes
- FURL config
- Fixes on Presentation templates and Query Components
- Thorough Testing
- Patch VCM to 7.6 SP1
- Another round of testing
Load Testing QA
- Use earlier scripts with webload
- Ask for the load tester desktop from Mark, that has all the scripts
- Will need to do it off hours
Post Upgrade:
- Upgrade to Portal 8.0?
------
FURL
- Configure FURL
- Remove FURL listener in config (Events>Pre create and update)
- set furl.exclude.sitename=false
- set linkprinter.impl
DPM Menu classes customization in vgn-ext-templating generic resource, rollback component and item region menu to use pre 7.4 classes
PIOCDA
- Include Michael's fixes to JSPs (Product detail etc.)
- Checkin changes in VSS